GFRC facade price in 1405 — approximate per-m² table

GFRC pricing is two separate worlds: simple flat panels and volumetric panels with custom molds. In Aban 1405 a flat panel is about 3 to 5 million Toman of material; volumetric and classic panels with custom molds start from 5 million and special designs go to 8 million and beyond. Complete installation with substructure usually lands around 3.8 to 8 million per m².

All prices are approximate, based on the company's supply rates (Namakaran Fakher Engineering Co.) and the Aban 1405 (Oct–Nov 2026) survey, with Tehran as the base; all rates exclude VAT. Daily material prices change and a firm figure is issued only with a detailed estimate for your project — all numbers must be re-confirmed at contract time.

The reason for this spread is the mold: with GFRC you pay part of the cost to the mold, not just the material. The more often a design repeats, the more the mold cost is divided over the area and the per-meter price falls. This one point usually explains 30 to 40 percent of the gap between offers.

Before ordering GFRC, take two things seriously: rear reinforcement of the panel (mesh and embedded plates for heavy loads) and the connection detail to the substructure. We calculate each panel's weight, engineer the substructure accordingly, and installation labor also starts from 2.5 million Toman per meter.

GFRC (glass fiber reinforced concrete)

Aban 1405 (Oct–Nov 2026)

GFRC panel prices vary widely with the design (flat to volumetric and classic); the figures are from the Aban 1405 market survey and the firm number comes from the factory quote.

ItemUnitApprox. range (Toman)
Simple flat GFRC panel (material)m²3,500,000 to 6,000,000
Volumetric / classic GFRC panel (material)m²5,000,000 to 8,000,000
Complete GFRC installation with substructure (with 20% overhead)m²9,500,000 to 17,000,000
Installation labor (material excluded)m²2,500,000 to 4,500,000

Steel and facade substructure

Aban 1405 (Oct–Nov 2026)

Priced per kilogram. Substructure weight ranges from roughly 6 to 10 kg per m² of facade depending on the system.

ItemUnitApprox. range (Toman)
Facade substructure — box profile, profiles and 2 mm sheetkg165,000
15×15 perforated plate (5 or 6 mm)pc400,000 to 500,000
Jenny anchorpc280,000 to 350,000

Engineering and overhead

Aban 1405 (Oct–Nov 2026)

This share is always in the final total. Wherever you do not see it, something has been cut from the quality of the work.

ItemUnitApprox. range (Toman)
Shop drawings and execution drawingsm² of facade250,000 to 600,000
Execution supervision and site managementm² of facade200,000 to 500,000
Profit, overhead and company ancillary costs% of total20

What pushes the price up or down?

Flat or volumetric panel and mold complexityHow often the module repeats on the facadePanel weight and rear reinforcementSubstructure density and heightFinal paint and patina

Prices in Tehran and other cities

GFRC panels are produced in the factory and transported to site; in other cities transport and crew accommodation are added to the estimate.

Prices in Tehran

Tehran is the base of our pricing. Glass and aluminum factories and professional installation crews are all here, so transport costs are low and finding a team is not hard. For high-rise towers, access costs (lifts, suspended platforms) are quoted separately in the estimate.

Iran Mall, Aftab 22 and several other residential towers are among our reference projects in Tehran. Whenever you like, you can visit one of our active sites — all the photos on this website are from real projects too.

Common questions about pricing

Other price pages

Related links

An exact estimate for your project

The tables are the starting point. Send your facade drawing and a few lines of description and we will provide a detailed, firm estimate — free and with no obligation.

Direct WhatsApp09396273115
Resume